Hydro Poole Update 5

Time for the latest update on the Hydro Pool and with the Pool now dug and concrete laid scaffolding is now being erected for the next phase. Site Manager Steve Plumb ” Initially we will be erecting timber shutters to form the pool walls, then we will start the steel reinforcing works and finally spray the concrete, this is a 3 to 4 week process to get the pool concreted and is a good milestone in the project as it really highlights the pool size and depths etc”. Stay tuned for more in a couple of weeks.

 